C-65.1, r. 4 - Regulation respecting certain service contracts of public bodies

Full text
12. The public body evaluates the tenders received, ensuring that the service providers are eligible and their tenders are compliant.
If the public body rejects a tender because the provider is ineligible or the tender is non-compliant, it must so inform the service provider and give the reason for the rejection no later than 15 days after awarding the contract.
A tender received after the closing date and time for receiving tenders may not, for that sole reason, be considered non-compliant if the delay is attributable solely to the public body.
O.C. 533-2008, s. 12; S.Q. 2018, c. 10, s. 20.
12. The public body evaluates the tenders received, ensuring that the service providers are eligible and their tenders are compliant.
If the public body rejects a tender because the provider is ineligible or the tender is non-compliant, it must so inform the service provider and give the reason for the rejection no later than 15 days after awarding the contract.
O.C. 533-2008, s. 12.